Name of the project: 10KW water experiment project of Nanjing University of Technology
Installed capacity: 10KW


Project destination: Institute of composite materials, Pukou campus, Nanjing University of Technology
Project construction time: August 2016 -2017 August, grid time in September 5, 2016