Release time:2017/08/28 Click:




Name of project: Xiangmi Lake, 71-1 9.3KW, Tong Town, Zhangjiagang
Installed capacity: 9.3KW


Project destination: No. 71-1 Xiangmi Lake, Tong Tong, Zhangjiagang
Project construction time: May 2017 -2017 May, grid time in May 20, 2017
Cooperation category: EPC total package