Name of project: self support micro powder 350KW roof distribution
Installed capacity: 350KW


The aim of the project: Jiangsu Yixing dingshuzhen Tao Industrial Park
Project construction time: August 2017
Cooperation category: contract energy management, own capital investment and holding power station.